Kent Rd, Toronto – Multi-Unit
Key responsibilities and scope of work included:
1-Drawings & Visual Planning:
Detailed layout drawings and elevation plans were created
3D renderings provided to help the client visualize the final design
Plumbing and electrical plans drafted for permit approval and execution
2- Sample Board Preparation:
A customized material and color sample board was prepared and presented to the client.
3- Project Execution & Management:
Full demolition of the existing bathroom
Installation of new plumbing and updated electrical systems
Moisture-resistant drywall and full waterproofing with Schluter® system & insulation
Installation of a ceramic shower base with frameless glass enclosure
Floor and wall tiling supply & install
Wall-mounted new vanity cabinetry production & install with the Vanity mirror
Date:
2025